How to install a buried earthing strip - trench depth, laying, jointing, connecting to electrodes, and the test before backfill.

A buried earthing strip ties electrodes together and forms the earth grid. It is laid in a trench about 500 to 600 mm deep, jointed with bolted or welded connections, bonded to each electrode, and tested before the trench is backfilled.

Installation steps

  1. Dig the trench 500 to 600 mm deep along the grid route.
  2. Lay the strip flat; avoid sharp bends that raise surge impedance.
  3. Joint strips with an overlap and two bolts, or exothermic weld; protect the joint.
  4. Bond the strip to each rod or pipe electrode with a clamp or weld.
  5. For high-resistivity soil, surround the strip with earth-enhancing compound.
  6. Measure earth resistance before backfill, then fill and compact.

Specify with confidence

CPRI-tested, standards-compliant products for this job — direct from the manufacturer.

Keep reading

Specifying for a real project?

Send your spec to Norton Power. Indicative quote within 4 working hours, Monday to Saturday.

Request a quote
Chat with us